FACILITES DESIGN FOR VARIOUS FACILITIES FUNCTION
Production rate variation occur due to:
- machine failures
- inherent variation in operator performance
-uncertainty in the arrival of components needed at individual workstation
Performance of the system is dependent on:
- layout of the facilities
- scheduling of production
- machine failure
- loading of the line
The disadvantages using this fixed automation system are:
- Very high equipment cost
- Inflexible in the number of products manufactured
- Inflexible layout
- Large deviation in production rates in case of equipment failure in the
line
Facility planning for the transfer line is relatively straightforward;
- Process equipment is arranged according to process sequence.
- Buffer sizes between workstation must be determines and
accommodated by several types of material handling devices such as
spiral type conveyors.
- Or the space between machine scan be increased to accommodate
buffer stock.
Frequently, the fixed automation system flow sequence is in straight line flow
structure as shown in Figure 4.1 (a) and U shape as in Figure 4.1 (b)
Figure 4.1 (a)
Figure 4.1 (b)