Page 44 - Facility Management Module
P. 44

FACILITES DESIGN FOR VARIOUS FACILITIES FUNCTION



                     Excersice 2:


                     Question :

                            Briefly describe the waste from the overproduction in Just In Time
                            manufacturing.


                     Answer


                             If the production lot increases unit production cost will increase as
                            well. Then manufacturer has to reorganize the rules to prevent
                            overproduction with the cost invested.





                          JIT philosophy can be categorized into five elements: visibility, simplicity,
                     flexibility, standardization, and organization.

                     1.  Visibility


                            It  can  be  obtained  by  the  following  technique:  electronic  boards  for  quick
                     feedback,  pull  system  with  kanbans,  problem  boards,  colored  standard  containers,
                     decentralized  storage  system,  marked  dedicated  areas  for  inventory,  tools,  etc.  'A

                     kanban  is  a  card  or  any  signal  used  to  request  or  authorize  production of  parts; it
                     contains  information  on  the  part,  the  processes  used,  identification  of  the  storage
                     area for the part, and the number of parts to produce.


                     2.  Simplicity
                            Simplicity  can  be  achieved  with  a  pull  system  with  kanbans,  simple  setup
                     changes,  certified  processes,  small  lot  sizes,  leveled  production,  simple  machines,
                     simple material handling, multifunctional workers, teamwork, etc.


                     3.  Flexibility
                            Flexibility can be achieved with short setup times, short production times, small
                     lot  sizes,  kanban  carts,  flexible  material  handling  equipment,  multifunctional

                     employees, mixed-model sequencing lines, etc.

                     4.  Standardization

                            Standardization of tools, equipment, pallets, methods, containers, boxes,
                     materials, and processes is pursued.