Page 453 - ANUAL REPORT MOH 2017
P. 453
No Project Name Date of Visit
6. Hospital Rembau 12-10-2017
7. Hospital Balik Pulau 10-10-2017
8. Hospital Seberang Jaya 09-10-2017
9. Hospital Bukit Mertajam 09-10-2017
10. Hospital Sungai Bakap 09-10-2017
11. Klinik Kesihatan Bandar Baru Ayer Itam 09-10-2017
12. Hospital Petra Jaya 14-08-2017
13. Hospital Sri Aman 14-08-2017
14. Membina Stor Farmasi Di Hospital Orang Asli,Gombak 18-07-2017
15. Hospital Raub, Pahang 24-05-2017
16. Klinik Kesihatan Kuala Betis Dan Cadangan Tapak PKD Stor
Berpusat , Gua Musang Kelantan 23-05-2017
17. Hospital Gua Musang 23-05-2017
18. Klinik Kesihatan Dengan Kuarters Di Chiku 3, Gua Musang 23-05-2017
(8CE,3DCE)
19. Cawangan Logistik Farmasi Negeri Sabah 20-04-2017
20. KK Menggatal, Kota Kinabalu 20-04-2017
21. Hospital Kapit, Sarawak 18-01-2017
22. Pejabat Kesihatan Kapit 18-01-2017
23. Klinik Kesihatan Kapit 18-01-2017
24. Hospital Alor Gajah 10-01-2017
25. Hospital Jempol (108 Katil) (Baru) 10-01-2017
26. Klinik Pergigian Pakar Kuala Pilah, Negeri Sembilan 10-01-2017
Source: Development Division, MoH
PROJECT COMPLETION AND HAND OVER
When a project is successfully completed, and upon issuance of the Certificate of Practical Completion
(CPC) by the Implementing Agency, a Meeting On Documents Checking Before Project Hand Over
is convened, involving the contractor, the consultants, the Implementing Agency, the client as well as
representatives from the Engineering Services Division and the Development Division. The purpose
of the meeting is to go through the checklist on the documentations that must be made available upon
project hand over, and other related matters. When the checklist is successfully complied and signed
off by all parties concerned, a recommendation will be made to the Secretary-General for project
hand over. Subsequently, mobilisation of resources and operations of the facility will follow. In 2017,
12 physical projects were successfully completed and handed over to MoH for utilisation and
operations of the facilities. The list of projects is enclosed in Table 8.
Table 8
List of Projects Completed And Handed Over to MoH, 2017
No. Project Names
1. Klinik Kesihatan (Jenis 3) Kota Damansara, Petaling Jaya
2. Penggantian Bumbung Di Keseluruhan Hospital Labuan
3. Klinik Kesihatan Kuala Lumpur (Sayap Baru Hospital Kuala Lumpur)