13. Special Conditions
Special conditions are one of the few documents included in this list that may not be necessary. However, if you
do choose to utilize special conditions, they would be included as an extension in the general conditions section.
14. Project Health and Safety Plan
The Construction Stage Health and Safety Plan is the main document for management of health and safety on
site. It should be prepared before construction work starts. However, it is a live and dynamic document that
will change and grow during the project and should be reviewed and updated on a regular basis
• The Project Health and Safety Plan is a document developed to secure the health, safety and welfare of
persons who will work or visit the site.
• It was also developed to control the emission of toxic substances into the atmosphere and control the keeping
and use of substances that might be hazardous to health. An outline of the Project Health and Safety Plan is
delineated in the appendix.
15. Schedule of Values
A schedule of values is provided by a contractor and lists all the work items from start to finish. It will allocate
the entire contract sum among the various portions of the work. The schedule of values is also a useful
management tool to form the basis for submitting and reviewing progress payments. This document can help
keep the cash flowing and bills paid on time.