3.1.1


        Site Boundaries


        The site boundary is the line beyond which the licensee or registrant does not own,
        lease, or otherwise control the land or property.
































           Site Paging



           A paging system is hard-wired into the building's infrastructure, allowing reliable
           mass communication. A network of speakers ensure that a message is
           communicated to every area of a building simultaneously. It's also possible to send
           pages to specific building "zones" if needed.




          Original Ground Level (OGL)


           The issues which render the importance of OGL survey prior to actual physical
           works are to establish the validity of the actual surface and the early design change
           prior to physical works.