INTERIM PROGRESS PAYMENT                                 WHO PREPARES INTERIM PAYMENT
                                                                  CERTIFICATE?
           In Malaysia, the standard forms of
           contract had provided clauses for the                      The Housing Grants, Construction and
           payment application and certification.                     Regeneration Act stipulates that interim
           The related payment clauses in respect                     or stage payments are due to any party to
           of the various conditions of contract in                   a construction contract that has a
           use in Malaysia are as the following:                      duration of more than 45 days. Therefore,
                                                                      almost all constructions contain
           In PAM 2006 Sub- Clause 30.1, requires                     provisions for interim payments.
           the Contractor to submit sufficient
           details or particulars to the Architect for
           him to value and ascertain the works                    HOW OFTEN ARE INTERIM
           (including materials and goods on site)                 CERTIFICATES ISSUED?
           and issue interim certificate for

           Contractor‟s entitlement to payment.                        The Housing Grants, Construction and
           The materials and goods on site shall be                    Regeneration Act stipulates that interim
           reasonably, properly and not                                or stage payments are due to any party to
           prematurely delivered with adequate                         a construction contract that has a
           protection against weather or any other                     duration of more than 45 days. Therefore,
           casualties                                                  almost all constructions contain
                                                                       provisions for interim payments.


       WHAT IS INTERIM CERTIFICATE
       MALAYSIA

             Interim certificates provide a mechanism for

             the client to make payments to the contractor
             before the works are complete. The Housing
             Grants, Construction and Regeneration Act,
             states that a party to a construction contract
             in excess of 45 days is entitled to interim or
             stage payments.