Page 47 - Interactive report Ar Site Practice
P. 47

IF I DO NOT HAVE A MAIN CONTRACTOR (CONSTRUCTION MANAGEMENT ROUTE)
        AM I RESPONSIBLE FOR PRACTICAL COMPLETION OR IS THE RESPONSIBILITY

        SPREAD ACROSS THE SUBCONTRACTORS THAT I EMPLOY?



                Where the construction management route is employed for the project, the Construction
                Manager should manage the practical completion process. This may be a Construction
                Management Consultancy, or a Main Contractor employed on a Construction
                Management basis.


                Each individual trade contractor will need to confirm back to the Construction manager
                when their section of the works are” complete”. From this, the construction manager
                will then issue a certificate of practical completion and accompanying payment notice to
                each of the trade contractors as and when required.



                Once all subcontractors have completed their works, the project will be “practically
                complete” and it is the Construction Manager’s responsibility to arrange for final
                inspection from building control (or approved inspector) and for the building
                regulations compliance certificate.





        DO I MONITOR PRACTICAL COMPLETION THROUGHOUT THE PROJECT AND WHAT
        DO I NEED TO RECORD IN ORDER TO DO SO?





                During a project, progress against the anticipated completion date can and should be
                monitored. The Contractor may be requested or obliged to submit master programmes
                at regular intervals within the construction periods, showing items of work both on and
                off critical paths. Delay to Practical Completion will only result as a delay to items of
                work that are on the Critical Path.


                The Contractor might monitor progress by “marking-up”, at monthly intervals, the site
                copy of the master programmes to indicate the actual progress of all activities shown
                thereon. If any circumstances arise that may affect the progress of Works, the
                Contractor shall put forward proposals or take other action as appropriate to minimise

                any delay and to recover any lost time. This may be accompanied by marked up drawings
                and photo evidence. That said, the Employer and Contractors QS will also review the
                programme on a regular basis as part of the Application for Payment Cycle.
   42   43   44   45   46   47   48   49   50   51   52