Page 44 - Interactive report Ar Site Practice
P. 44

There is no absolute definition of practical completion and case law is very complex.
                There is some debate about when practical completion can be certified and whether

                it  can  be  certified  where  there  are  very  minor  (de  minimis)  items  'not  affecting
                beneficial occupancy' that remain incomplete. A draft building owner's manual.





                It  is  important  to  note  however,  that  the  defects  liability  period,  which  follows
                certification of practical completion, is not a chance to correct problems apparent at
                practical completion, it is the period during which the contractor may be recalled to
                rectify  defects  which  appear  following  practical  completion.  If  there  are  defects
                apparent  before  practical  completion,  then  these  should  be  rectified  before  a
                certificate of practical completion is issued.





                This can put the contract administrator in a difficult position, as both the contractor
                and  the  client  may  be  keen  to  issue  the  certificate  (so  the  building  can  be  handed
                over),  and  yet  defects  (more  than  a  deminimis)  are  still  apparent  in  the  works.
                Issuing  the  certificate  could  render  the  contract  administrator  liable  for  problems
                that this causes, for example in the


                      1.   Calculation of liquidated damages,
                     2. The position in relation to performance bonds
                     3. The release of retention when it is not certain that the works will be completed





                On construction management contracts, a separate certificate of practical completion
                must be issued for each trade contract. Once all trade contracts (or all trade contracts
                for a particular section of the works) have been issued, the construction manager issues
                a certificate or project completion (or sectional completion). The same is true on
                management contracts, where each works contract must be certified individually.




                 Practical completion is not a term recognized in some recently developed contracts
                 such as PPC 2000 and other partnering contracts which simply refer to 'completion'.
                 This can put the contract administrator in a difficult position as to when the project
                 becomes 'useable' by the client.