Page 46 - Interactive report Ar Site Practice
P. 46

HOW TO OBTAIN A CERTIFICATE OF PRACTICAL COMPLETION?


                When the Contractor believes the Works are practically complete, he must contact the
                Engineer to request the Certificate.



                The Engineer must answer in 14 days and if he feels the Works aren’t yet practically
                complete, he must give the Contractor a list of the work which must be done to make
                the Works complete.



                 Once the Contractor has properly completed the work on the Engineer’s list, the
                 Engineer should issue the Certificate of Practical Completion.




           AS A DEVELOPER (EMPLOYER), HOW DO I PROVE THAT PRACTICAL COMPLETION

           HAS NOT BEEN MET?


                 To achieve Practical Completion, the Contractor must comply with clause 2.37 (JCT
                 Design and Build) and provide the Employer with contractor’s design documents and any
                 related information specified in the Contract that show or describe the work (i.e. As
                 Built Drawings, O & M Manuals which show the operation and maintenance of the

                 works). The Contractor must also comply with the obligations placed upon him under
                 the CDM regulations cl.3.16 (JCT) which require that the Contractor carries out all Duties
                 as Principal Designer and Principal contractor should they be so named as these within
                 the particulars.



                 Practical Completion requires sign off from the Local Authority Building Control or the
                 Approved Inspector. This is a fit for occupation certificate and a fire life and safety
                 certificate will also be required. All services should be tested and commissioned with all
                 relevant certificates provided. Acoustic testing and air tightness tests should be carried
                 out to ensure compliance with any statutory regulations or any requirements as set out

                 within the Contract Documents.
   41   42   43   44   45   46   47   48   49   50   51