Page 73 - Lecture Notes DCC3113
P. 73
FEEDBACK ON EXERCISE 4
1. State FOUR (4) methods for the construction of road base course in flexible pavement
Macadam Crusher-Run Road Base (4 marks)
_____________________________________________________________________________________
Dry Bound Macadam Road Base
_____________________________________________________________________________________
Wet-Mix Road Base
_____________________________________________________________________________________
Bituminous Roadbase
_____________________________________________________________________________________
Cement-Treated Base
_____________________________________________________________________________________
2. State FOUR (4) adventages of using flexible pavement in Malaysia
To provide a level/flat surface for a more comfortable and safe journey (4 marks)
_____________________________________________________________________________________
To receive and distribute the load of the vehicle to the ground layers
_____________________________________________________________________________________
To protect the sub-grade layers from damage due to exposure of climate change.
_____________________________________________________________________________________
To provide a level/flat surface for a more comfortable and safe journey
_____________________________________________________________________________________
To receive and distribute the load of the vehicle to the ground layers
_____________________________________________________________________________________
To protect the sub-grade layers from damage due to exposure of climate change
_____________________________________________________________________________________
3. Describe the functions and application of prime coats during road construction of flexible
pavement
(8 marks)
Is a sprayed application of a cutback or emulsion asphalt applied to the surface of untreated roadbase using
pressure distributor at the rate of 0.5 – 1 liter/m2
Is poured between the road base surface and binder course
The temperature must be according to the specifications stipulated.
MC-70 (50°C -70°C), SS-1K (25°C - 45°C) cured for 24 hours to achieve maximum penetration
The function of prime coat are
- Coat and bond any lose material
- Harden or toughen the surface
- Waterproof the base during construction
- Plug capillary voids
- Provide adhesion between the base and the next course