Page 337 - ANUAL REPORT MOH 2017
P. 337
Table 4
List of Some Projects Implemented In 2017
Year 2017
Type of projects implemented No Of CPC
Projects issued in Status
2017
(i) Kesihatan Awam (BP 200)
35 projects completed
a. Projek sambungan 39 1 1 projects in progress
3 projects in planning phase
1project in progress
b. Projek baharu 3 -
2 projects in planning phase
(ii) Kemudahan Hospital (BP 300)
30 projects completed
a. Projek sambungan 41 - 8 projects in progress
3 projects in planning phase
b. Projek baharu 0 -
(iii) Kemudahan Anggota/ Kuarters (BP 900)
2 projects completed
a. Projek sambungan 5 - 1 project in progress
2 project in planning phase
b. Projek baharu 0 -
(iv) Projek Naiktaraf/ ubahsuai Sistem Kejuruteraan (BP 600)
21 projects completed
a. Projek sambungan 28 6 4 projects in progress
3 projects in planning phase
1 project in progress
b. Projek baharu 5 -
4 projects in planning phase
(v) Peralatan dan Kenderaan (BP 1100)
a. Projek sambungan 1 - 1 project in progress
b. Projek baharu 1 - 1 project in planning phase
(v) Sinking Fund
25 projects completed
a. Projek sambungan 32 9
7 projects in progress
1 project completed
b. Projek baharu 10 1
9 projects in progress
(vi) Projek Khas
a. Pembinaan Klinik Kesihatan Kuala 1 1 1 project completed
Lumpur (Sambungan)
336 ANNUAL REPORT 2017 MINISTRY OF HEALTH MALAYSIA