        2.1.1 DOCUMENT REQUIRED PREPARED BY THE CONTRACTOR PRIOR

        TO SITE POSSESSION






        DEFINITION OF                                               Possession of site

                                                                    ➢ Where the contractor have the right
                                                                         to enter the site , occupy and use the
        ➢According to the new oxford                                    site and carry out the specified
            dictionary second edition, site” is                         works

            defined as a piece of land where a
            building was is or will be

            “Possession “ is defined as the state
            of having or owning something







          PERFORMANCE BOND

          ➢ Issued to one party of a contract as a
              guarantee against the failure of the

              other party to meet obligations
              specified in the contract.



          ➢ Usually provided by a bank or an
               insurance company to make sure a
               contractor completes designated

               projects.



          ➢ Typically in the amount of 50% of the
              contract amount, but can also be
              issued for 100% of the contract
              amount.