Page 78 - test2
P. 78

occurred between April 19 and April 20 was a possible contributing cause of
                   the blowout.

                              D.     Flow Path Cause


                                   1.    Production Casing Annulus Cement Barrier and the 9‐7/8 Inch

                                         Wellhead Seal Assembly

                          As discussed above, the following evidence weighs against the possibility
                   that hydrocarbons flowed through the production casing annulus cement barrier
                   and the 9‐7/8 inch wellhead seal assembly:

                       1)  On September 9, 2010, Dril‐Quip technicians confirmed with a lead
                          impression tool that the 9‐7/8 inch wellhead seal assembly remained
                          properly seated in the 18‐3/4 inch high pressure housing, where it had
                          been placed on April 19, 2010 prior to the flow of hydrocarbons.
                       2)  On September 10, BP conducted a 30‐minute pressure test of the 9‐7/8 inch
                          production casing annulus that confirmed the lack of annular
                          communication.
                       3)  On September 11, the lock‐down sleeve seal was successfully pressure
                          tested to 5,200 psi, which tended to prove that the hanger was properly
                          seated.
                       4)  On September 22, Schlumberger’s logging data determined that “free” gas
                          was not present below the BOP to 9,318 feet measured depth.
                       5)  On October 7, BP’s perforation of the 9‐7/8 inch casing between 9,176 feet
                          and 9,186 feet found that no u‐tube flow occurred from the casing to
                          annulus.
                       6)  During well intervention operations, ROV observation determined the
                          wellhead seal assembly was intact.  In addition, subsequent to removing a
                          portion of the 9‐7/8 inch production casing, original 13.8‐14.0 ppg mud
                          was discovered between the 16 inch intermediate casing and 9‐7/8 inch
                          production casing.
                       7)  Pictures taken from the DDII relief well rig at the time the hanger and seal
                          assembly were extracted from outside hanger and seal assembly showed
                          no signs of erosion from annular flow.

                   Based on this evidence, the Panel concluded that hydrocarbons did not flow
                   from the production casing annulus cement barrier and the 9‐7/8 inch wellhead
                   seal assembly during the blowout.




                                                             73
   73   74   75   76   77   78   79   80   81   82   83