VI.        Challenges at the Macondo Well


                          BP and Transocean encountered a number of problems during drilling
                   and temporary abandonment operations at the Macondo well – including kicks,
                   stuck pipe, lost returns, equipment leaks, cost overruns, well scheduling and
                   logistical issues, personnel changes and conflicts, and last minute procedure
                   changes.  These problems led rig personnel and others to refer to Macondo as the
                                     160
                   “well from hell.”

                              A.     Kicks and Stuck Drill Pipe

                          BP company records and testimony from rig personnel establish that at
                   least three well control events and multiple kicks occurred during drilling and
                   temporary abandonment operations at the Macondo well.  The first well control
                   event occurred on October 26, 2009, when the well was being drilled by
                   Transocean’s Marianas rig.  The second well control event occurred on March 8,
                   2010, after the Deepwater Horizon had replaced the Marianas and resulted in a
                   stuck drill pipe.

                                                                                            161
                          It took the crew at least 30 minutes to detect the March 8 kick.   This
                   delay raised significant concerns among BP personnel overseeing the operation
                   about the ability of personnel on the Deepwater Horizon to promptly detect kicks
                   and take appropriate well control actions.

                          In a post‐blowout interview, John Guide, a BP wells team leader, stated
                   that, at the time (March 2010) he was concerned that the Deepwater Horizon team
                   had become “too comfortable” with itself because of its good track record for
                   successfully drilling difficult wells, and that its members missed potential
                   indications of problems during the March 8 event that they should have
                           162
                   caught.

                          Other individuals responsible for operations at Macondo expressed

                   concern about the events of March 8:


                   160  Testimony of Mike Williams, Joint Investigation Hearing, July 23, 2010, at 35 (stating that the
                   Deepwater Horizon crew had used the name “well from hell” on a prior well and also used the
                   term on the Macondo well because on both wells the crew encountered similar lost circulation,
                   stuck pipe, and kick problems).
                   161  BP‐HZN‐MBI00221686.
                   162  BP‐HZN‐BLY00125447.