Page 25 - Flight International (January 2020)
P. 25

ROTORCRAFT



































                                                                                   Mollis facility faces challenging weather
        Kopter                                                                           conditions during winter months


        ❯❯  At that point, Kopter was preparing to fly   warnings when approaching speed, altitude   dampers on the main rotor head to improve
        the programme’s third prototype – effectively   or power thresholds.     ride quality, plus an assortment of aerody-
        the aircraft to be used to mature the configura-  Hovering was also ruled out because of the   namic and handling tweaks, such as to the
        tion. But because the issue was found to afflict   likely strain this would put through the hous-  vertical fin and horizontal stabiliser.
        all of the gearbox components produced, the   ing. “There were several times when I won-  Chief test pilot Richard Grant says that the
        only way to get the helicopter into the air was   dered whether [flying] was a good idea,” con-  ride of the SH09 is already as smooth as or
        a significant period of test and evaluation to   fesses one pilot.        even smoother than other helicopters out
        prove – to itself and to the European Union   But in September last year, came the “long-  there, although at certain parts of the enve-
        Aviation Safety Agency (EASA) – that flights   awaited retrofit” of the new gearbox housing,   lope there are “weaknesses” which “is what
        with the parts would be safe within a certain   sourced from a different supplier: “Now we   we are working on”.
        flight envelope.                      can fly the helicopter rather than the helicop-  Approaching top speed “we are seeing a
          Then, when EASA had given its permis-  ter flying the pilots,” says Riccobono, “and   little bit of motion in the nose”, he says,
        sion for those flights to start – the first sortie   explore the full envelope.” But with the first   which is what some of the changes are de-
        took place in November 2018 – the dramati-  sortie using the new component only having   signed to counteract.
        cally reduced envelope meant much slower   taken place last autumn, envelope expansion   The final configuration will be reflected in
        headway than expected.               work is still in its early stages. Nonetheless,   two further test articles: pre-serial (PS) aircraft
                                             Riccobono sees that “significant progress” has   4 and 5, which will arrive from mid-2020.
        DECENT PROGRESS                      been made: weight has been incrementally in-  A substantial amount of certification flying
        “The envelope restrictions in terms of air-  creased to 2.6t – close to the target of 2.85t –   will be carried out by PS4 in Pozzallo, leading
        speed and manoeuvres were so severe that it   and the helicopter has been taken to 10,000ft   to an aircraft approved to operate at 16,000ft
        really hampered progress,” says Riccobono.   density altitude.           density altitude and at temperatures between
          Nonetheless, with persistence that eventu-  Test activities have been aided by the estab-  -10°C (14°F) and 35°C. That will be followed
        ally translated into “decent progress”, despite   lishment of the dedicated facility in Pozzallo.   by cold weather and hot-and-high campaigns
        the “limitations of the flawed gearbox”.   Staff undertake six-week rotations at the site,   using PS5, in Alaska and Colorado, respec-
          But flights were anything but simple.   and the final Sicilian sortie of 2019 – coinci-  tively, clearing the SH09 to operate at temper-
        Take-offs with the “crippled” gearbox were   dentally the prototype’s 100th – took place on   atures as low as -40°C.
        a  “nightmare”, says Riccobono: pilots   4 December (the flightplan reads: “conduct a   Riccobono says that even without the
        were forced to perform an ungainly shuffle   photo shoot in the vicinity of Modica”).  changes the SH09 would be certifiable, but
        to  become airborne without overstressing   “[The aircraft] is giving us more than I   Kopter’s ambition is not to produce an aircraft
        the housing.                         could expect – we are really using it now as I   that is merely adequate. “We always want to
          “You had to suppress your natural reaction.   would call it a workhorse in order to get the   be better than the others,” he says.
        [The technique] goes against anything   final configuration frozen. The pilots are quite   The intention is to be “a little bit above the
        you  have been taught,” says test pilot   happy with it,” says Lowenstein.    EASA certification level”, he says, which
        Michel Dekkers.                        Data gathered from the flights with the new   includes having the safety performance of
          Similar restrictions were applied to flight   gearbox housing will be used to inform   a  CS-29 helicopter – essentially crash-
        as well: test pilots describe sorties where   improvements to the helicopter that will be   worthiness and bird strike resistance – in an
          either Riccobono or flight-test engineer   implemented in early 2020. Modifications   aircraft certificated to EASA’s CS-27 small
        Adam Reynolds were constantly issuing   include changes to the elastomeric blade   rotorcraft standard.


        26  |  Flight International  |  28 January-3 February 2020                                      flightglobal.com