Page 29 - pd282-May20-mag-web_Neat
P. 29

Salt Lake thinks big




                    with Lake Way development




            he coronavirus pandemic has done lit-  port despite the current global conditions   de-risking is well advanced ahead of the
         Ttle to halt Salt Lake Potash Ltd’s pro-  reinforce Swiericzuk’s argument that Lake   major works around the processing plant
         gress on its Lake Way potash develop-  Way  represents  a  unique  opportunity  in   construction.
         ment project in Western Australia.  the Australian resources space; a robust   “The  big  spend will be putting  the  big
          While the global pandemic has strangled   commodity combined with a low-cost   Lego pieces together later in the year and
         most of the international economy with a   capex and opex scenario.      Q3 and Q4 will see a very fast build,” Swi-
         vice-like grip, Salt Lake (SO4) continued   “Potash has a great thematic. The agri-  ericzuk said.
         its serene progress at Lake Way, near   culture sector is strong and fertiliser prices   Project development has become in-
         Wiluna in the Northeastern Goldfields.  have been incredibly resilient in the face   creasingly difficult as governments impose
          In April, the company completed civil   of the coronavirus,” he said. “Lake Way,   more  stringent  restrictions  on  movement
         earthworks  at  its  processing  plant  site,   like all the brine producers in Australia and   but according  to  Swiericzuk  Lake  Way’s
         paving the way for plant construction which   around the world, will be in the lowest cost   timetable has not be delayed by the pan-
         is due for completion by the end of 2020.  quartile. And, it is smothered by infrastruc-  demic.
          Speaking to Paydirt in April, SO4 man-  ture with the Goldfields pipeline and high-  “It is an opportune time in our schedule
         aging  director  Tony  Swiericzuk  said  the   way on the edge of the lake and the Wiluna   for this to occur. We finished Stage 2 on-
         company was on target to hit its own ambi-  township and airstrip within 15km.   lake civils in early February and the off-lake
         tious deadlines.                      “It is very attractive from a support in-  civils in April. So, we are in a period of fi-
          “We want to be commissioning the plant   frastructure perspective, which is helping   nalising engineering and procurement and
         by the end of 2020,” Swiericzuk said.  fast-track the project and supports the low   then we will be in baseline operation of the
          SO4 is already well advanced with Lake   capex and opex numbers.”       ponds.”
         Way’s development. It began construction   SO4’s decision to stage Lake Way’s   If SO4 can stick to its development time-
         of the on-lake solar evaporation ponds and   construction has been assisted by the pot-  line, Lake Way could be commissioning by
         trenches in early 2019 and by the beginning   ash development process which allows for   the end of the year.
         of 2020 had 400ha of brines under sun.   sequencing.                      “It is a simple flowsheet and product and
          These ponds will produce the feed for the   “A potash project is very different to a   we have done plenty of trials with our har-
         processing plant.                   metals project. It is a more spaced time-  vest salts and been through different labs
          “We have got more than 50% of our   frame than a traditional metals project and   and flowsheets and circuits and got some
         on-lake delivery – trenching and ponds   we intentionally set about fast-tracking the   fantastic results in terms of quality,” Swier-
         – completed,” Swiericzuk said. “Now we   project by staging it. That means we could   iczuk said.
         are faced with the plant and NPI which will   get the long-lead task of precipitation out   “This management team has done a few
         roughly cost $100 million. We completed   of the way early,” Swiericzuk said.   commissioning projects together and we
         the civil earthworks for the plant site and   “The first stage was to get brine as fast   know you’ll always have little bumps along
         have locked in a lot of the long-lead items   as  we  could  under  sun  because  that  is   the road, but this is not a technical plant;
         on fixed lump sum terms.”           how we make ore. The salts precipitate   there are no high temperatures or pressure
          SO4 raised $20 million via a placement   out and that’s basically your orebody so   or acid. So, we are expecting a rapid ramp-
         in April to provide further cash reserves for   you are creating a ROM feed. We started   up. We plan for a rapid ramp-up and then
         the next stage of construction.     that process in January 2019 and hit the   halve the schedule for your internal target.”
          The capital raising was the fourth in the   ground running. Stage 1 was construc-  Once Lake Way is up and running, SO4
         past 15 months, bringing the total of funds   tion of 125ha of solar evaporation ponds   can turn attention to the other eight lakes it
         raised to more than $76 million. In addition,   which have been under sun since March   has in its WA portfolio.
         the company has a $US165 million debt fa-  last year and by December we completed   “We are laser focused on Lake Way, we
         cility with Taurus Funds Management.   Stage 2, a further 275ha.”        want to get that built, get cashflow going
          SO4’s  ability  to  attract  financier  sup-  The staged approach has meant project   and get the balance sheet in order,” Swier-
                                                                                  iczuk said. “Once we do that, we can look
                                                                                  at other things. This is a multiple lake port-
                                                                                  folio and while I jokingly say we’re going
                                                                                  to create the Pilbara of potash, the nine-
                                                                                  lake portfolio we have does lend itself to
                                                                                  creating a SOP province. Building ponds
                                                                                  and trenches is all control-C/control-V
                                                                                  stuff.  We  now  understand  the  optimum
                                                                                  methodology and how to construct them
                                                                                  fast and cheaply. The plant is the same,
                                                                                  off-the-shelf, so we will gladly be stepping
                                                                                  across other lakes as the market can take
                                                                                  the product.”
                                                                                                    – Dominic Piper

                                     SO4 started on-lake construction in March 2019 as part
                                         of its staged approach to Lake Way’s development
                                                                                      aUSTRaLIa’S PaYDIRT   MaY 2020   Page 29
   24   25   26   27   28   29   30   31   32   33   34