                          Process Control -  Programming & Progress


                 a.  PURPOSE

                     The  purpose  of  the  procedure  is  to  ensure  timely  project  completion  through
                      programming the required works and monitoring actual progress.

                 b.  SCOPE OF APPLICATION

                     This procedure applied to all programming and progress reporting activities and all
                      personnel involved in such activities.

                 c.  DEFINITIONS
                      None

                 d.  CROSS REFERENCE
                            Quality Manual Clause f.9

                            Inspection & Testing QAP 100
                 e.  RESPONSIBILITY FOR APPLICATION

                     General  Manager,  Planning  Engineer  & Project  Manager are  responsible  for  the
                      application of this procedure

                 f.  PROCESS

                      f.1  Programming
                           f.1.1  All necessary contract document will be handed to the Planning Engineer
                                  upon his appointment / selection. Such document may include.
                                     Terms and condition of contract

                                     Contract Specification
                                     Bill of quantities

                                     Contract Drawings and Amendments
                                     Plans of existing services
                                     Tender Programme

                                     Site investigation report, if any
                                     Record of existing site conditions.

                           f.1.2  The planning Engineer should study the above information and the overall
                                  concept of operations for the building work. Where possible he should
                                  visit the site.
                           f.1.3  The planning Engineer shall procedure a master construction programme
                                  for the purpose of programming, co-ordination an further monitoring of
                                  work progress. The programme should include all required project activities
                                  from start to finish, including pre-construction activities (e.g. Mobilization)