f.4  The Project Manager shall arrange for all necessary resources to be mad available
                           in order to affect mobilization

                      f.5  Where early site possession is available mobilization and planning may be carried
                           out simultaneously.
                      f.6  The Project Manager is responsible for ensuring that all required notices to Local
                           authorities have  been  placed  or are  being  arranged  so as  to ensure  timely
                           mobilization and avoid delay when construction work commences.

                 g.  RECORDS
                     Where a site layout plan is a contractual requirement it will be maintained by the Project
                      Manager as required by the contract

                 h.  FILING
                     The master copy of this procedure is filed by the Management Representative, together
                      with other procedures, under the number QAP 91.
                 i.  ATTACHMENT

                     None



                                                       