f.4 The Project Manager shall arrange for all necessary resources to be mad available
in order to affect mobilization
f.5 Where early site possession is available mobilization and planning may be carried
out simultaneously.
f.6 The Project Manager is responsible for ensuring that all required notices to Local
authorities have been placed or are being arranged so as to ensure timely
mobilization and avoid delay when construction work commences.
g. RECORDS
Where a site layout plan is a contractual requirement it will be maintained by the Project
Manager as required by the contract
h. FILING
The master copy of this procedure is filed by the Management Representative, together
with other procedures, under the number QAP 91.
i. ATTACHMENT