1.6 Project design with ETS – The principles
The following steps represent the chronological order for project design with ETS.
Carry out the ETS settings
Read in or convert product databases
Create the project with the necessary data
Set up the structure of the project (building structure/bus topology)
Insert KNX products (devices with corresponding application) into the building
structure
Set the parameters of the KNX products according to requirements
Create group addresses
Link the group objects of the KNX products with the group addresses
Assign the configured KNX products to the bus topology (final definition of the
individual address)
Assign the configured KNX products to the installed functions (optional)
Check the project design
Print out the documentation
Save the project
It is possible to deviate from this sequence in individual cases. Some steps can be
omitted for smaller projects. Additional steps are necessary in large projects (team
projects).