SECTION 11.0 – REQUIREMENT OF APPROVING AUTHORITIES APPENDICES
c) Certificate of Completion and Compliance (CCC)
Upon satisfactory completion of the work and obtaining clearance or
confirmation from the Local Authority and the respective technical
departments, the PSP shall issue CCC for the said project.
d) Fire Certificate Designated
All designated premises must have a fire certification issued by JBPM
as per Fire Services Act 1988. The PSP shall compile the necessary
documents such as a copy of CCC, approved building plans, and land
ownership for the client to submit for the fire certification.
11.1.5 The successful tenderer shall be responsible to liaise with the relevant
Local Authority including other technical agencies regarding the
infrastructure facilities required such as water supply, electrical power,
telecommunication, firefighting requirements, drainage, sewerage,
access roads, rubbish disposal, etc., and thus to provide all the
requirements concerning them for this project.
11.1.6 Whenever required by the by-law or regulations, the successful tenderer
shall be responsible to prepare and submit drawings, calculations, and/or APPENDICES
documents to the relevant authorities for approval through the local
practicing professionals who are registered with the relevant boards.
11.1.7 Prior to submission to the approving authorities, the PD shall agree with
all designs, drawings, and specifications. A copy of all correspondences
and replies to/from the approving authorities shall be extended to the PD.
11.1.8 The successful tenderer shall be responsible to inform the respective
technical departments regarding the project’s development, such as the
Town Planning Department, the Local Authorities Council, etc.