Page 117 - JKR HEALTH FACILITY ARCHITECTURAL NEEDS STATEMENT 2021 EDITION_Neat
P. 117

SECTION 11.0 – REQUIREMENT OF APPROVING AUTHORITIES                                                                                                               APPENDICES



                                  c)  Certificate of Completion and Compliance (CCC)

                                     Upon satisfactory completion of the work and obtaining clearance or
                                     confirmation  from the  Local Authority and  the respective technical
                                     departments, the PSP shall issue CCC for the said project.

                                  d)  Fire Certificate Designated

                                     All designated premises must have a fire certification issued by JBPM
                                     as per Fire Services Act 1988. The PSP shall compile the necessary
                                     documents such as a copy of CCC, approved building plans, and land
                                     ownership for the client to submit for the fire certification.

                        11.1.5    The successful tenderer shall be responsible to liaise with the relevant
                                  Local Authority  including other technical agencies regarding  the
                                  infrastructure facilities required such as water supply,  electrical power,
                                  telecommunication,  firefighting requirements, drainage,  sewerage,
                                  access  roads,  rubbish  disposal,  etc.,  and  thus  to  provide  all  the
                                  requirements concerning them for this project.

                        11.1.6    Whenever required by the by-law or regulations, the successful tenderer
                                  shall be responsible to prepare and submit drawings, calculations, and/or                                                          APPENDICES
                                  documents to the  relevant authorities  for approval through  the local
                                  practicing professionals who are registered with the relevant boards.

                        11.1.7    Prior to submission to the approving authorities, the PD shall agree with
                                  all designs, drawings, and specifications. A copy of all correspondences
                                  and replies to/from the approving authorities shall be extended to the PD.

                        11.1.8    The successful  tenderer shall be  responsible  to inform  the respective
                                  technical departments regarding the project’s development, such as the
                                  Town Planning Department, the Local Authorities Council, etc.



















                                                                                                                                                                                                                         APX-01
                                                                                                     108                                       2021 EDITION                                       HEALTH FACILITY ARCHITECTURAL NEEDS STATEMENT
                        2021 EDITION                                       HEALTH FACILITY ARCHITECTURAL NEEDS STATEMENT