Causes of variation orders
A: Owner-related variations B: Consultant-related variations C: Contractor-related variations D: Other variations
Change of plans or scope Change in design by Contractor's lack of involvement Weather conditions
by owner consultants in design
Change of schedule by owner Errors and omissions in design Unavailability of equipment Safety considerations
Owner’s financial problems Conflicts between contract Unavailability of skills Change in government
documents regulations
Inadequate project objectives Inadequate scope of work for Contractor’s financial difficulties Change in economic regulations
contractor
Replacement of materials/ Technology change Contractor’s desired profitability Socio-cultural problems
procedures
Impediment in prompt Value engineering Differing site conditions Unforeseen problems
decision-making process
Obstinate nature of owner Lack of coordination Defective workmanship
Change in specifications by Design complexity Unfamiliarity with local conditions
owner
The customer may change Inadequate working drawing Lack of specialised construction
the specifications for a very details manager
good reason.
Inadequate shop drawing details Fast-track construction
Consultant’s lack of judgement Poor procurement process
and experience
There may be a lack of
Consultant’s lack of knowledge of Lack of communication communication by the
available materials and equipment contractor.
Honest wrong belief of consultant Contractor’s lack of
judgement & experience
Consultant’s lack of required data Long lead procurement
Obstinate nature of consultant Honest wrong belief of contractor
Ambiguous design details Complex design and technology
Design discrepencies (inadequate Lack of strategic planning
design)
Non-compliant design with Contractor’s lack of required data
govt. regulations
Non-compliant design with Contractor’s obstinate nature
owner’s requirements
Change in specifications by
consultant
p Figure 4.12 Causes of variation orders