Page 237 - The City and Guilds Textbook: Plumbing Book 1 for the Level 3 Apprenticeship (9189), Level 2 Technical Certificate (8202) and Level 2 Diploma (6035)
P. 237

Chapter 4 Planning and supervision

                Variations in work

                Nearly all construction projects will encounter changes or variations during the
                design and construction process. Because of this, many construction contracts
                include provision for a variation clause. The term variation usually means a
                change, modification, alteration, revision or amendment to the original contract
                and how works are to be carried out.
                In order to solve problems related to changes to a project, the project team
                must be equipped to analyse the variation, anticipate its immediate effect on
                other parts of the work programme and then effectively manage the new work.

                Variation order
                A variation order is a document that records any agreement made with a client    INDUSTRY TIP
                to alter the existing work specified in a building contract.
                                                                                            Producing the variation order
                Variation in the work that would involve any change to the agreed contract   as early as possible will save
                price for the work must be agreed and approved in writing by the owner before   money, as one of the problems
                a variation order can be put into action. A variation can impact on timescales   with reaching agreement is the
                for completion and any order must include details of both cost and time     time the whole process takes.
                changes.                                                                    Sometimes an independent
                                                                                            company can be brought in to
                If a variation of work is caused, for example, by poor installation or lack of   quickly resolve variation issues
                ability to complete a task properly, then the contractor could be liable for   if there is poor communication
                any subsequent costs. A problem with the installation may have been identified   and co-ordination on a project.
                by the clerk of works and, if it is found that the routing of exposed pipework
                is not acceptable, it would then alter the agreed design. A discussion with the
                contractors must take place and the reasons for the change, and its impact on
                time and cost, must be carried out with the customer.

                If the customer suggests changes after the contract has been signed, then they
                will have to bear the costs related to delays or additional material and design
                to complete the work. All changes are to be confirmed in writing as written
                communications have the advantage of providing a permanent record.

                Causes of variation orders
                The chart in Figure 4.12 shows a range of causes for variations and is helpful
                when assessing where liability rests.
























                                                                                                                225





        9781510416482.indb   225                                                                                    29/03/19   8:56 PM
   232   233   234   235   236   237   238   239   240   241   242