Page 242 - The City and Guilds Textbook: Plumbing Book 1 for the Level 3 Apprenticeship (9189), Level 2 Technical Certificate (8202) and Level 2 Diploma (6035)
P. 242

The City & Guilds Textbook: Plumbing Book 1

                                            Step 5: Reviewing your risk assessment
                                            and updating it if necessary

                                            Quite often a plumber has to return to the same area of work on a servicing and
                                            maintenance contract, and circumstances could have changed. If the example of the
                                            boiler room is used again, then there could be new hazards such as the storage of
                                            combustible materials or even chemicals in the vicinity of the appliances. Someone
                                            may have damaged the main equipotential bonding at the gas meter, or a contractor
                                            could have inadvertently partially blocked a temperature relief discharge pipe.
                                            It is therefore advisable that you look at the existing risk assessment for the
                KEY TERMS                   job location, and make a note of any new changes and actions required. It is
                Risk calculation formula:   essential that the risk assessment stays up to date. In a maintenance work plan
                this is a method of using   it is good practice to plan and review dates for risk assessments.
                a formula of multiplying
                likelihood by consequences   Risk calculation formulas
                to provide a number that
                quantifies the level of risk   A risk calculation formula is also known as ‘ranking the risk’, and results in
                for a particular job.       assigning a number to each risk. Start with an assessment of the likelihood
                Quantitative approach:      of an accident, then proceed with listing the consequences. This is called the
                ranking a risk with a number.  quantitative approach.

                                            The formula for ranking risk with the quantitative approach is shown in Table 4.4.

                                              Table 4.4 Risk calculation formula
                        Likelihood of an accident occurring           Consequences of an accident occurring
                                                         Scale value                                    Scale value
                        No likelihood                   0             No injury or loss                0
                        Very unlikely                   1             Treated by first aid             1
                        Unlikely                        2             Up to 3 days off work            2
                        Likely                          3             More than 3 days off             3
                        Very likely                     4             Specified major injury           4
                        Certainty                       5             Fatality                         5
                                                           Calculation of risk factors
                                                          Likelihood × Consequence
                                       Calculated figure                                  Action
                        Figures between 1 and 6                       Minor, but monitor closely
                        Figures between 8 and 15                      Significant, immediate control action
                        Figures between 16 and 25                     Critical, all activities must stop until risk reduced

                                            Worked calculation

                                            Imagine an apprentice is asked to solder pipework in the loft space of a house
                                            that was built in 1960. They are required to remove the galvanised CWSC.
                                            What precautions should be taken, and what are the risks to the plumber
                                            and others?
                                            There are several risks associated with this scenario. Access to the work area is to
                                            be carefully considered, along with the likelihood and consequences of an accident
                                            occurring, and the provision to be put in place to reduce the risk.
          p  Figure 4.17 Soldering pipework
                230





        9781510416482.indb   230                                                                                    29/03/19   8:56 PM
   237   238   239   240   241   242   243   244   245   246   247