Page 23 - APPLIED PROCESS DESIGN FOR CHEMICAL AND PETROCHEMICAL PLANTS, Volume 1, 3rd Edition
P. 23

10                       Applied Process Design for Chemical  and  Petrochemical  Plants


























                                                         O'frlf(Ml























                                Figure 1-9. Typical  process and piping flow diagram.  By permission, E.  E.  Ludwig [56].




            percent  range.  Even  these  costs  can  be  reduced  if all   Flowsheet Presentation
            minute  detail  is avoided,  and only  basic  decision  making
            piping  is  included.  The  necessary  model  structure  and   Experienced flowsheet layout personnel all  emphasize
            rough  block  outline  equipment for  a  $1  million  hydro-   the  importance  of breaking  processes  into  systems  and
            carbon  compression  and  processing  plant costs  around   logical parts of  systems such as reaction, compression, sep-
            $1,000 to $2,000.                                     arating,  finishing,  refrigeration, storage,  etc., for detailed
                                                                  drafting. This point cannot be overemphasized, since con-
                                                                  siderably more space is needed for final  completion of all
              Paton  [15]  reports  total  model  costs  of 0.4 to  1.0  per-   details than  is usually visualized at first.  The initial  layout
            cent of erected  plant costs  for a  $1  million  plant.  These   of the key equipment should be spread farther than looks
            are  actual  costs  and  do  not reflect profits.  Material  costs   good to the eye. In fact,  it probably looks wasteful of draw-
            are less  than  10 percent of total  model costs,  and usually   ing space.
            less  than  5  percent.  For a  $30  million  plant model  costs   Later as  process  and  sometimes  service  lines,  valves,
            run  as  low  as  0.1  percent.  These  are  for  models  which   controls  and  miscellaneous  small  accessories  are  added
            include plant layout,  piping layout,  and piping details.  If   this  "extra"  space  will  be  needed  to  maintain  an  easily
            simpler models are used the costs should be less.     readable  sheet.  As  this  develops,  attention  should  be