Page 92 - test2
P. 92

after the displacement of the mud from the wellbore.  The plan also increased the
                   depth of the cement plug to be set in the well as a barrier to flow.  BP chose to
                                                                                                  203
                   hang 3,000 feet of drill pipe below the lock‐down sleeve to weigh it down.
                   Having chosen to do this, BP believed that it needed to set the cement plug
                   deeper than normal to increase the amount of weight on the lock‐down sleeve.
                   The approved plan also called for two negative tests.  The first negative test was
                   to be to the wellhead with a seawater gradient on the kill line.  The second
                   negative test was to be conducted after displacing with seawater down to 8,367
                   feet.  Further, the approved plan called for the cement plug to be set in seawater
                   after displacement of mud from the wellbore.

                          BP’s temporary abandonment plan also called for the cement plug to be
                   set in seawater after displacement of mud to 3,300 feet below the mud line.  This
                   created a risky situation – after displacement of the mud, the well would be in an
                   underbalanced condition and at risk of a well control event.  In addition, BP had
                   already eliminated the second cement barrier that would normally be set above
                   the top cement wiper plug.  This further increased the well control risks.

                              C.     The Use of Lost Circulation Material as Spacer

                          BP’s plans for displacement of the mud from the riser at the Macondo well
                   called for the use of spacer fluid, which is used to separate the drilling mud from
                   the seawater during displacement.  The plans included the use of two different
                   “pills” of spacer.  The pills to be used were a blend of leftover lost circulation
                   material that had been mixed on the rig.  The lost circulation material (material
                   provided by MI‐SWACO with the trade names Form‐A‐Set and Form‐A‐
                   Squeeze) had been primarily used to prevent additional lost returns at the well.
                   BP had never used this type of spacer before, and it did not know whether the
                   spacer would be compatible with the synthetic based mud that it was displacing.
                   BP also did not have any information about the long‐term stability of the
                                                                    204
                   interface between the spacer and the seawater.   The Panel found no evidence
                   that BP had provided the rig crew with design specifications for the spacer.

                          The Panel reviewed evidence, including BP internal emails, that indicated
                   that BP chose to use the lost circulation materials as a spacer to avoid having to
                   dispose of the materials onshore.   If the materials were circulated through the
                                                      205

                   203  Testimony of Ronald Sepulvado, Joint Investigation Hearing, July 20, 2010, at 145.
                   204  Testimony of Steve Robinson, Joint Investigation Hearing, December 8, 2010, at 114.
                   205  BP‐HZN‐MBI00262887.


                                                             87
   87   88   89   90   91   92   93   94   95   96   97