Page 461 - APPLIED PROCESS DESIGN FOR CHEMICAL AND PETROCHEMICAL PLANTS, Volume 1, 3rd Edition
P. 461

Process Safety and Pressure-Relieving Devices                        427

           relief valve must be  at least ,If  in.  in pipe size,  [1]  Par UG-   quately known. They should be researched or investigated
           128  (see  [79]).                                     by laboratory testing for possible runaway conditions and
                                                                 then  the  kinetic  and  heat/pressure  rise  calculations
                         Selection and Application               should be performed,  even if some  assumptions  must be
                                                                 made  to  establish  a  basis.  Refer to  later  paragraphs  and
           Causes of System Overpressure                         the  American  Institute  of  Chemical  Engineers  Design
                                                                Institute  for Emergency  Relief [67]. At the  time  of aves-
             Figure 7-14,  Operational Check Sheet [25], lists 16 pos-   sel  or  pressure/vacuum  system  failure,  the  calculations
           sible causes of  overpressure in a process system. There are   for the effected pressure-relief  devices are always reviewed
           many others,  and each system  should be  reviewed for its   by  plant management and  the  Occupational  Safety  and
           peculiarities.  System  evaluation is the heart of a realistic,   Health  Administration  (OSHA)  inspectors.  A  few  notes
           safe  and yet economical  overpressure  protection installa-   on causes of process system failures are noted below,  with
           tion on any single equipment or any group of equipment.   additional comm  en ts in API-521  [13,  33a,  b,  c]
           Solving formulas with the wrong basis and/  or data can be
           disastrous.  The following should be reviewed:
                                                                   Failure  of Cooling  Water:  assume  all  cooling  mediums
                                                                fail, determine relief  capacity for the total vapors entering
             1. The sources of possible overpressure
             2. Maximum overpressure  possible from all  sources   the vessel,  including recycle streams.  See  [3]  and  [10].
             3. Maximum rate of  volume increase at the burst pres-
               sure, and temperature at this condition.            Reflux Failure:  (a)  At top of distillation column, capaci-
             4.  Length of duration of overpressure.            ty is total overhead vapor  [iO], (b)  when source of heat is
                                                                in  feed  stream,  capacity  is  vapor  quantity  calculated  in
           Capacity Requirements Evaluation for Process         immediate feed zone  [3],  (c)  when reboilers supply heat
           Operation (Non-Fire)                                 to system, capacity is feed plus  reboil  vapors  [3]. Each sit-
                                                                uation must be examined carefully.
             Each  system  and  item  of equipment should  be  exam-
           ined  for operational  safety  as  set forth  by  specific  plant
           area  (and  process  fluids)  requirements  and  the  codes   Blocked Outlets on Vessels:  (a)  For liquid, capacity is max-
           previously cited. The codes particularly  [10, 13, 27, 33a, b,   imum pump-in  rate.  (b)  For liquid-vapor system, capacity
           c]  establish  guides  based  on  wide  experience,  and  are   is total  entering vapor plus any generated in vessel  [ 10].
           sound requirements for design. Relief  capacity is based on
           the most severe requirement of a system, including possi-
           ble  two-phase flow  [67]. A  system is  generally  equipment   Blocked  Outlets  and  Inlets:  for  systems,  lines  or  vessels,
           or  groups  of  equipment  which  is  isolated  by  shut-off   capable  of being filled with  liquid and  heated  by  the sun
           valves.  Within  these  isolated  systems  a  careful  examina-   or  process  heat,  require  thermal  relief to  accommodate
           tion  of the  probable  causes  of overpressure  is  made  [6].   the liquid expansion (assuming vaporization is negligible).
           Figures  7-15,  7-16,  and  7-17  are  suggested  guides  [25].
           Capacities  are  calculated  for  conditions  of temperature   Instrument  Failure:  assume  instrument  control  valves
           and  pressure  at actual  state of discharge.  Final  discharge   freeze  or fail  in  open  position  (or closed,  which  ever is
           pressure is the set pressure  plus overpressure.     worse), determine capacity for relief based on flows,  tem-
             It  must  be  emphasized,  that  the  determination  of the   peratures,  or  pressures  possible  under  these  circum-
           anticipated  maximum  overpressure volume at a  specified   stances.  The  judicious  selection  of  instrument  failure
           pressure  and  temperature  is vital  to  a  proper protection   sequence  may  eliminate  or  greatly  reduce  relief valve
           of the process system. The safety relief  calculations should   requirements.
           be performed at the actual worst conditions of the system,
           for example,  at the allowable  accumulated pressw·e  and
           its  corresponding  process  temperature.  These  can  be   Equipment Failure: pumps, tubes in heat exchangers and
           tedious  and  perhaps  time-consuming  calculations,  but   furnaces, turbine drivers and governor,  compressor cylin-
           they  must not be  "glossed" over but developed  in a man-   der valves  are  examples  of equipment which  might  fail
           ner that accounts  for the  seriousness  of the  effort.  They   and  cause  overpressure  in  the  process.  If an  exchanger
           must be documented carefully  and preserved permanently.   tube  splits  or  develops  a  leak,  high  pressure  fluid  will
             The situation is just as critical, if  not more  so, for run-   enter the low side,  overpressuring either the shell  or the
           away  reactions  or  reaction  conditions  that  are  not ade-   channels and associated system as  the case  may be.
   456   457   458   459   460   461   462   463   464   465   466